Over 2,500 Km of roads constructed under Bharatmala in Andhra Pradesh
Over 2,500 Km of roads constructed under Bharatmala in Andhra Pradesh
NEW DELHI: Under Bharatmala project, about 2,520 Km of roads amounting to Rs 44 thousandcrore have been envisaged in the State of Andhra Pradesh. Details of Bharatmala Roads is as under:n
n
n n |
||
Length nn(in Km.) | Status | |
Madanapalli ?Pileru Section of NH-71 | 54.86 | DPR in progress |
Pileru ? Cherlopalli Section of NH-71 | 50.94 | DPR in progress |
Renigunta to Poyya section of NH-71 | 55.2 | DPR in progress |
Kadapa – Renigunta (NH-40) (Chennai – Puttur – Kadapa – Nandyal – Kurnool) | 138 | DPR in progress |
AP / KN Border – Alur – Adoni section of Hasan – Raichur | 83.89 | DPR in progress |
Visakhapatnam ? Raipur Section:nnDevelopmental works of NH-26 from Ondarangi ? Vizianagaramin the state of Andhra Pradesh (Visakhapatnam ? Raipur section). | 70 | DPR in progress |
Sub Total | 247.00 | |
B. Under Inter Corridor Routes | ||
Mydukur ? Badvel section of NH ? 67 | 41 | DPR in progress |
Badvel ? Nellore | 106.77 | DPR in progress |
Sub Total | 147.77 | |
C. Under NHAI / NH (O) | ||
DPR for upgradation of the highway starting from junction with NH-44 at Anantapur ? Giddalur of NH 544D in the State of Andhra Pradesh to Two / Four lane with paved shoulder configuration (Pkg-I & II) | 139.00 | DPR in progress |
Two lane with paved shoulder of Anantapur ? Giddalur of NH 544D (Pkg-III) (Bugga to Kaipa) | 57.400 | Bids Invited |
Two lane with paved shoulder of Anantapur ? Giddalur of NH 544D (Pkg-IV) (Kaipa to Giddalur) | 77.569 | Bids Invited |
DPR for upgradation of the highway starting Giddalur to Guntur of NH 544D (Vinukonda ? Guntur) in the State of Andhra Pradesh to Two / Four lane with paved shoulder configuration | 83.00 | DPR in progress |
DPR for Upgradation of Kurnool ? Dornala section of NH-340C to Two/Four lane with paved shoulder configuration | 124.15 | DPR in progress |
Sub Total | 481.119 | |
D. Ring Roads | ||
6-laning of Chilakaluripet Bypass on NH-16 under NHDP Phase-V on BOT(Toll) | 16.384 | DPR in progress |
Feasibility Study Report for Construction of Outer Ring Road around Vijayawada ? Guntur ? Tenali Urban Agglomeration in the States of Andhra Pradesh on Green Field Alignment under NHDP Phase-VII | 189 | DPR in progress |
Sub Total | 205.384 | |
E Costal Roads | ||
Kathipudi ? Ongole stretch of NH-216 (2l+PS/4L) | 363 | Work in progress in 9 packages |
Sub Total | 363 | |
F Residual Works in NHDP | ||
Davulapally ? Markapuram ? Vagampalli ? Dornala and Penchalkona ? Yerpedu section of NH 565 (2L+PS) (Implemented in 4 packages) | 287 | Work completed |
Mydukur ? Nellore section of NH-67 (Implemented in 3 packages) (2L+PS) | 149.5 | Work completed |
Ibrahimpatnam ? Chandragudem and Chandragudem-A.P Telangana border section of NH 221 (Implemented in 2 packages) (2L+PS) | 70.3 | Work completed |
Dornala ? Penchalakona section of Nh-565 (2L+PS) | 42 | Work in progress |
Karnataka/AP Border-Gooty section of NH-67 (4L) | 57 | Work in progress |
Nagarjunsagar Dam- Davulpally section of NH-565 | 47 | DPR complete |
Davulpally reserve forest section of NH-565 | 22 | DPR in progress |
Sub Total | 674.8 | |
G Connectivity of Backward districts and Religious and Tourist centres | ||
Malkangiri on NH 326- Chintapalle-Naripattanam ? Waddai – Chodavaram-Sabbavaram&Narsipatnam ? Tuni section | 280 | DPR in progress |
Route starting from NH-565 Gotlagattu ? Podile ? Uppalapadu ? Chimakurti – Ongole on NH-16. | 107 | DPR in progress |
Sub Total | 387 |